Final | 10/17/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Tom Saunders
|
|
|
final for bldg P Phone #: ###-#### Inspection requested via web by Todd Hall...ok to final
|
Final | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PART |
Tom Saunders
|
|
|
final for Office unit only interior Phone #: ###-#### Inspection requested via web by Todd Hall..interior of office ok...ok to move furniture in office
|
Electrical Rough-In | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Tom Saunders
|
|
|
ceiling grid Office unit Phone #: ###-#### Inspection requested via web by Todd Hall... ceiling grid in office ok to cover
|
Permanent Service | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Hall p/s u/g n ok
|
Permanent Service | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Hall Feeders need installed Main breaker required when over 6 throws of the hands
|
Electrical Rough-In | 9/9/2018 | 9/10/2018 | 9/10/2018 | A | PASS |
Mark Moncarr
|
|
|
underground inspection for conduits between southern perimeter buildings including across new entrance at south side of property off Common St. (3) conduit locations. Call Todd if questions Phone #: ###-#### Inspection requested via web by Todd Hall Ok cover conduits between buildings. 2 locations 18", 3rd location atleast 24".
|
Rough-In Permanent Service | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | NR |
Tom Saunders
|
|
|
Roughin for walls in office building. Service for office building PLEASE inspect as late in the afternoon as possible. we are trying to wrap up today. Phone #: ###-#### Inspection requested via web by Todd Hall...
service not ready....changed to rough for walls
|
Electrical Rough-In | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PASS |
Tom Saunders
|
|
|
Roughin for walls in office building. Service for office building PLEASE inspect as late in the afternoon as possible. we are trying to wrap up today. Phone #: ###-#### Inspection requested via web by Todd Hall...
rough in walls only
|
Electrical Rough-In | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Tom Saunders
|
|
|
underground Phone #: ###-#### Inspection requested via web by Todd Hall....complete underground for Phase 1 buildings...ok to cover
|
Electrical Rough-In | 8/1/2018 | 8/2/2018 | 8/2/2018 | P | PART |
Rock A. Hudson
|
|
|
inspection for underground from office building to gate, pole light and storage buildings. Please inspect early afternoon so trenches can be filled back before end of day. Also need consult on another item on site. please call Todd Phone #: ###-#### Inspection requested via web by Todd Hall Called as requested, no answer, left message. Underground for entry area, gate, light pole, and to buildings P, and B only. Rough in ok cover
|