Final | 9/3/2019 | 9/3/2019 | 9/4/2019 | P | PASS |
Mark Moncarr
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Eric Brown Ok final. Talked to electrician about recepts for cabinet countertop on N wall in kitchen. It is considered work suface. Plug mould was added to cover this requirement. In living room, I am not considering cabinets to left and right of fireplace as wall space. They are book shelves.
|
Final | 8/30/2019 | 9/3/2019 | 9/3/2019 | A | CANC |
Mark Moncarr
|
|
|
###-#### Was re-called for PM.
|
Final | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | CANC |
Mark Moncarr
|
|
|
Later in the afternoon would be better but happy to see you when you can make it. Thanks Mark. Phone #: ###-#### Inspection requested via web by Eric Brown Rescheduled for 9/3
|
Electrical Rough-In | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Mark Moncarr
|
|
|
Floor heat in upstairs master bathroom. Thank you Phone #: ###-#### Inspection requested via web by Eric Brown Ok cover flr heat mstr.
|
Electrical Rough-In | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | PASS |
Daryl DeGrange
|
|
|
Floor heat. Two downstairs bathrooms Phone #: ###-#### Inspection requested via web by Eric Brown listed floor heat 2 basement bathrooms
|
Electrical Rough-In | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | CANC |
Rock A. Hudson
|
|
|
Floor heat rough in. The two downstairs bathrooms. Thank you Phone #: ###-#### >> Inspection requested via web by Eric Brown Inspection cancelled from web by: Eric Brown
|
Rough-In Permanent Service | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | PASS |
Mark Moncarr
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Eric Brown p/s u/g n ok
|
Electrical Rough-In | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | PASS |
Mark Moncarr
|
|
|
soffit rough in inspection for cover. Please call and I will meet on site. Thank you! Phone #: ###-#### Inspection requested via web by Eric Brown Ok cover soffits. Fire hats in place.
|
Conference | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | DONE |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Eric Brown Discussed downstairs switch location.
|
Electrical Rough-In | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Mark Moncarr
|
|
|
Floor outlets in concrete slab Phone #: ###-#### Inspection requested via web by Bonnie Page Ok cover floor 2 floor outlets and island stub.
|