Final | 10/23/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
James Ady
|
|
|
Final on ADU behind residence. Please call Eric ###-#### to schedule access. Thank you! Phone #: ###-#### Inspection requested via web by Eric Brown Final ok
|
Conference | 9/21/2018 | 9/21/2018 | 9/21/2018 | A | PASS |
James Ady
|
|
|
please call to schedule conference. Eric ###-#### Thank you Phone #: ###-#### Inspection requested via web by Eric Brown Talked about items needed to final out ADU. GFCI protection, panel schedule, dish lockout.
|
Electrical Rough-In | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
James Ady
|
|
|
please call to schedule conference. Eric ###-#### Thank you Phone #: ###-#### Inspection requested via web by Eric Brown Ok to cover J-boxes under stairs and top of stair case.
|