Final | 11/14/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
James Ady
|
|
|
Ready for final inspection Phone #: ###-#### Inspection requested via web by Paul Stewart final ok
|
Electrical Rough-In | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | PASS |
James Ady
|
|
|
Paul Phone #: ###-#### Underground to swim spa and underground from service to sub panel ok to cover
|
Conference | 10/3/2018 | 10/5/2018 | 10/5/2018 | P | DONE |
James Ady
|
|
|
If possible I need the electrical consultation after 3pm. Phone #: ###-#### Inspection requested via web by Paul Stewart Discussed 100a feed to Swim spa sub pannel. Feeding a 2 pole 50a and a 2 pole 60a GFCI breaker from panel. When to call for inspection, Burrial depth of conduit and sch80 above ground
|