Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mark Moncarr
|
|
|
Need final on upstairs Inspection requested via web by dennis mcneely Ok final upstairs. 2 other permits on house. 1 for main level ELE18-02998, and another for the garage ELE18-01105. Both still in issue status.
|
Electrical Rough-In | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Mark Moncarr
|
|
|
rough-in upper story can use back door an climb stairway I will be over there around 1 2finish couple things rewire 3way and add box that im missing. can meet u if want im working close by make sure u have access Phone #: ###-#### Inspection requested via web by dennis mcneely Ok cover upstairs
|
Electrical Rough-In | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PASS |
Rock A. Hudson
|
|
|
oops will be there around noon an make sure you have access Phone #: ###-#### Inspection requested via web by dennis mcneely Level 2 floor rough in ok cover
|
Electrical Rough-In | 10/12/2018 | 10/12/2018 | 10/12/2018 | P | FAIL |
Eric Story
|
|
|
relocated wiring through floor joists that used to be attic extend existing wiring to enter new walls through floor. need cover for new floor access is in back of house up the ladder Phone #: ###-#### Inspection requested via web by dennis mcneely No ladder on site
|