Final | 11/28/2018 | 11/29/2018 | 11/29/2018 | A | PASS |
Eric Story
|
|
|
Solar light poles have been installed and working. No street power has been ran into the poles, purely solar powered. Phone #: ###-#### Inspection requested via web by Jim Noll Final ok
|
Electrical Rough-In | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Eric Story
|
|
|
2 solar light pole bases at Shoshone Park before concrete pour. Phone #: ###-#### Inspection requested via web by Jim Noll Man. Fact sepc will be sent to insure if a grounding electrode will be needed on solar light pole, contractor will provide one at this time to continue with concrete pour. Light bases ok to cover
|