Description
New: Full electrical installation for Building 37 interior, through three different phases. Installation includes conduit, wiring, gear, panels, lights, lighting control, receptacles, and telecomm.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final1/28/20191/29/20191/29/2019APASS
DetailsJames Ady
Please call Bobby for final inspection of 1st and 2nd floor area C and for final inspection of Building 37. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Final ok
Final1/28/20191/29/20191/29/2019ACANC
DetailsJames Ady
Please call Bobby for final inspection of 1st and 2nd floor area C and for final inspection of Building 37. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Final1/23/20191/23/20191/23/2019PPART
DetailsJames Ady
Please call Bobby for final inspection of office furniture on 1st floor and final of areas A and B first floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Remaining items are fitness area, Panel schedules on all floors Basketball Court and N Restrooms 1st floor. Area A and B furniture final ok
Electrical Rough-In1/11/20191/11/20191/11/2019PPASS
DetailsJames Ady
Please call Bobby for ceiling grid inspection on 2nd floor and 1st floor ceiling inspection. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Spinning room ceiling only ok to cover
Final1/9/20191/9/20191/9/2019APART
DetailsJames Ady
Please call Bobby for phase 2 TCO final inspection. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Phase 2 TCO ok
Final1/8/20191/8/20191/8/2019APART
DetailsEric Story
Please call Bobby for phase 2 final inspection of 2nd floor (verify office furniture connections are ready and covers are in place). Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
2nd floor furniture and all electrical associted on 2nd floor ok
Final1/7/20191/7/20191/7/2019PFAIL
DetailsEric Story
Please call Bobby for final of 2nd floor office furniture connections and phase 2 part final. R/I inspections for area C walls and area B pre walk on 1st floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Furniture missing baseplates@ 2 rows of furniture in-op
Electrical Rough-In1/7/20191/7/20191/7/2019PPASS
DetailsEric Story
Please call Bobby for final of 2nd floor office furniture connections and phase 2 part final. R/I inspections for area C walls and area B pre walk on 1st floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo
Pre-walk for furniture install area B ok, Level 1 area C Locker room,fitness walls ok to cover
Electrical Rough-In1/3/20191/3/20191/3/2019APASS
DetailsJames Ady
Please call Bobby for ceiling grid inspection in 3 rooms of area C. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 1st floor area B rooms. (not C as noted on request)
Final12/28/201812/28/201812/28/2018PNR
DetailsJames Ady
TCO final for 2nd floor, R/I 1st and 2nd floor fitness rooms. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor cubicals not installed. N. side checked and ready for final.
Electrical Rough-In12/28/201812/28/201812/28/2018PPASS
DetailsJames Ady
TCO final for 2nd floor, R/I 1st and 2nd floor fitness rooms. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 1st floor locked hard lids ok to cover. wall in 2nd floor fitness room ok to cover
Electrical Rough-In12/27/201812/27/201812/27/2018APASS
DetailsJames Ady
Please call Bobby for inspection of ceilings on 1st and 2nd floor and wall R/I inspection on 2nd floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 1st floor area C ceiling only ok to cover other areas listed not ready.
Electrical Rough-In12/21/201812/21/201812/21/2018PPASS
DetailsJames Ady
Please call Bobby for inspection of grid ceiling on 1st floor. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Drop lid only area A ok to cover
Electrical Rough-In12/19/201812/19/201812/19/2018PPASS
DetailsJames Ady
R/I inspection spinning room area 2. Call Bobby, thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Spinning room ceiling only ok to cover
Electrical Rough-In12/19/201812/19/201812/19/2018APART
DetailsJames Ady
Please call Bobby for inspection of ceiling in area C 1st floor and grid ceiling on 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo 2nd floor area C minus Spinning room 202. 1st floor restrooms area C Ceilings only ok to cover
Final12/11/201812/12/201812/12/2018PPART
DetailsJames Ady
Please call Bobby to walk 3rd, 2nd, 1st, and Link for phase 1 final inspection. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo phase 1 Partial final ok
Electrical Rough-In12/11/201812/11/201812/11/2018APASS
DetailsJames Ady
Please call Bobby for R/I inspection of 1st floor area A. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed ok to cover
Electrical Rough-In12/10/201812/10/201812/10/2018APASS
DetailsJames Ady
Please call Bobby for R/I inspection of mill work in 1st floor lobby. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area listed ok to cover
Final12/6/201812/7/201812/7/2018ANR
DetailsJames Ady
Please call Rafael for part final phase 1 of B37. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo Several areas not ready for electrical install. 2nd floor elevator lobby ceiling. 1st floor restrooms missing access in ceiling for light J-box. 1st floor main lobby flooring not in place for floor box install. Missing millwork for security desk and and South wall sink area. Misc walls unfinished and not ready for switch install. Sky bridge unfinished and open to elements. Power shall remain off untill widows installed.
Electrical Rough-In12/7/201812/7/201812/7/2018PPART
DetailsJames Ady
Please call Rafael for part final phase 1 of B37. Thanks. Phone #: ###-#### Inspection requested via web by Rafael Castillo 3rd floor cubical reinspect. Corrections made on North side funiture. Receps checked on South side cubicals. Missing several lower covers through out. Will check to make sure they are installed at final. Roof top service recep needed for mini-split condensor units as per 210.63. Recep shall be accessible.(Refer to definition of accessible as applied to equipment. Shall not be guarded by locked doors)
Electrical Rough-In12/6/201812/6/201812/6/2018APASS
DetailsJames Ady
Please call Rafael for wall R/I inspection of 1st floor milkwork. Phone #: ###-#### Inspection requested via web by Rafael Castillo Millwork ok. (Note: Inspections done under permit ELE18-01206 on interior of building, other than ground work, shall serve as rough in on this permit.)