Final | 4/8/2019 | 4/10/2019 | 4/10/2019 | P | PASS |
Tom Saunders
|
|
|
Would also like to do consult for next project Phone #: ###-#### Inspection requested via web by Thomas Bond...ok to final
|
Electrical Rough-In | 2/20/2019 | 2/22/2019 | 2/22/2019 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Thomas Bond` Main bath only ok to cover
|
Electrical Rough-In | 2/18/2019 | 2/19/2019 | 2/19/2019 | P | NR |
Tom Saunders
|
|
|
consultation for moving electrical boxes Phone #: ###-#### Inspection requested via web by Thomas Bond... conference scheduled will schedule rough inspection when ready
|
Conference | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Tom Saunders
|
|
|
consultation for moving electrical boxes Phone #: ###-#### Inspection requested via web by Thomas Bond...homeowner has previously done work...consult done at that time and he is confident in doing current work...ok
|