Permit Information
Permit NumberELE19-01582
StatusFinaled
Name DOHERTY ELECTRIC
Site Address 10577 W FAIRVIEW AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
New: Electrical for new gas station
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final2/5/20202/6/20202/6/2020APASS
DetailsTom Saunders
Final inspection - Call Shannon with any questions 208.369.3336 Phone #: ###-#### Inspection requested via web by Deb Morton...
ok to final
Final1/30/20201/31/20201/31/2020AFAIL
DetailsMark Moncarr
Final inspection please contact Shannon on site Phone #: ###-#### Inspection requested via web by Deb Morton
1. Circuits B1-6, 14, 17, 20, 28 and 39 need GFI protection.
2. Doors for refers on S side need installed so wiring can be completed. Open junction boxes at this time. I did not get on roof to check RTU's, or open fuel dispensers in front.
Conference1/17/20201/17/20201/17/2020PDONE
DetailsTom Saunders
Call Shannon on job site before you go out. Needing to discuss a couple things. Phone #: ###-#### Inspection requested via web by Deb Morton...discussed wiring of gas dispensor..clssification and wiring methods...wiring floor box
Electrical Rough-In1/16/20201/17/20201/17/2020APASS
DetailsTom Saunders
Ceiling inspection - please see Shannon Stepp onsite with any questions. Phone #: ###-#### Inspection requested via web by Deb Morton...
grid areas ok to cover...5 outlets above grid will be moved into grid
Permanent Service12/19/201912/20/201912/20/2019APASS
DetailsRock A. Hudson
Shannon at ###-#### Phone #: ###-#### Inspection requested via web by Deb Morton
41.6k Available fault current on a 65 k rated main. p/s u/g n ok
Permanent Service12/18/201912/19/201912/19/2019ANR
DetailsTom Saunders
Permanent service inspection, please contact Shannon at ###-#### Phone #: ###-#### Inspection requested via web by Deb Morton...needing AFC label
...rescheduled to next day AM
Electrical Rough-In12/4/201912/5/201912/5/2019APASS
DetailsTom Saunders
Bathroom and Hallway inspection to hard lid cover call Brett with any questions Phone #: ###-#### Inspection requested via web by Deb Morton...ok to cover hard lids and cooler wall
Electrical Rough-In11/26/201911/27/201911/27/2019APASS
DetailsRock A. Hudson
Exterior Walls Rough-in. Please contact Brett Jenkins. Phone #: ###-#### Inspection requested via web by Deb Morton
Interior walls added to exterior request.
Walls only rough in ok cover.
Electrical Rough-In10/30/201910/30/201910/30/2019PPASS
DetailsTom Saunders
Underground inspection, late morning or early afternoon please. Contact Shannon onsite. Phone #: ###-#### Inspection requested via web by Deb Ipsen...underslab pump feeds to panel rm and in/under slab feeds thruought building
Conference10/28/201910/28/201910/28/2019PPASS
DetailsTom Saunders
Conference concerning underground work. Please contact Shannon onsite. Phone #: ###-#### Inspection requested via web by Deb Ipsen..depths of pipes into panel room from pumps for pump controls
Electrical Rough-In10/22/201910/23/201910/23/2019PPASS
DetailsJames Ady
Underground Inspection, Shannon is the contact Phone #: ###-#### Inspection requested via web by Deb Ipsen Underground to entry sign only ok to cover
Electrical Rough-In10/17/201910/17/201910/17/2019PPASS
DetailsTom Saunders
underground inspection Phone #: ###-#### Inspection requested via web by Deb Ipsen...
feeds from transformer to building...ID Power verified as well...ok to cover
Electrical Rough-In10/11/201910/14/201910/14/2019APASS
DetailsTom Saunders
Electrical inspection for a uffer.
Shannon is the contact.
Phone #: ###-#### Inspection requested via web by Deb Ipsen...uffer ok to cover...perimeter underground for monument sign and air compressor ok to cover
Temporary Service10/3/201910/4/201910/4/2019ACANC
DetailsTom Saunders
Temporary power pole that had to be relocated.Shannon will be the contact. Phone #: ###-#### Inspection requested via web by Deb Ipsen...wrong permit used for temp service...will need to open another permit bor original temp service permit...call city of Boise
Electrical Rough-In6/18/20196/18/20196/18/2019PPASS
DetailsTom Saunders
Under ground inspection. Shannon is the contact. Phone #: ###-#### Inspection requested via web by Deb Ipsen...
underground tanks to pumps ok to cover
Conference5/8/20195/8/20195/8/2019PFAIL
DetailsRock A. Hudson
On this date at approx 3pm drove by job site and witnessed general contractor inside temporary service panel performing work. When asked admitted doing work to hook up flexible cord with twist lock. 327 took photo of GC drivers license and informed all work shall be performed by electrical contractor permitted for this sites work.