Final | 8/7/2019 | 8/9/2019 | 8/9/2019 | A | PASS |
James Ady
|
|
|
Chad Vanorden is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Final ok
|
Electrical Rough-In | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | PASS |
James Ady
|
|
|
Ceiling Inspection, contact is Chad Vanorden ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Ceiling throughout only ok to cover
|
Electrical Rough-In | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
James Ady
|
|
|
Wall rough-in, Chad Vanorden is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Talked about Existing House panel and Meter Base in main electrical room. Top breaker is at 7ft and meter base has Cardboard blank. Both items need addressed. Discussed cleaning up old electrical and removing any violations in work areas. Misc walls in breakroom and front office area ok to cover.
|