Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Rock A. Hudson
|
|
|
Install complete per approved plans; the stamped and approved plans are on site; For any questions about the work done for this project, call Jed at ###-####; For any questions about the plans or design, call Ryan at ###-####; thanks guys
the solar disconnect and the panel are all exterior, in front yard, so you can show up any time. The homeowner will be at work but everything is accessible for ya Phone #: ###-#### Inspection requested via web by Ryan King Final ok
|
Electrical Rough-In | 6/20/2019 | 6/21/2019 | 6/21/2019 | P | PASS |
James Ady
|
|
|
listing inspection for solar equipment; they guys should be getting there to throw panels at noon; rough -in can happen anytime from 12 pm on Phone #: ###-#### Inspection requested via web by Ryan King listing only ok
|