Final | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PASS |
Tom Saunders
|
|
|
Last six units final and final building. Phone #: ###-#### Inspection requested via web by Kevin Burke...101,102,201,202,301,302...and exterior building complete
|
Final | 9/22/2019 | 9/23/2019 | 9/23/2019 | A | PART |
Daryl DeGrange
|
|
|
3rd 6 units from north end Phone #: ###-#### Inspection requested via web by Kevin Burke Units 103,203,303 and 104,204,304 partial final A/C units Need to identify white conductors as current carrying
|
Final | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PART |
Tom Saunders
|
|
|
2nd six units from north end. Phone #: ###-#### Inspection requested via web by Kevin Burke... next units 105, 106, 205, 206, 305, 306...ok
|
Final | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | PART |
Rock A. Hudson
|
|
|
first 6 from the N // Kevin Phone #: ###-#### first thing in AM...rescheduled from Friday 107, 108, 207, 208, 307, 308 TCO ok
|
Final | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | CANC |
Tom Saunders
|
|
|
first 6 from the N // Kevin Phone #: ###-####...discussed with contractor...rescheduling for Monday AM first thing..9/9/19
|
Final | 9/4/2019 | 9/5/2019 | 9/5/2019 | P | CANC |
Tom Saunders
|
|
|
Final first 6 units from the North. Phone #: ###-#### >> Inspection requested via web by Kevin Burke Inspection cancelled from web by: Kevin Burke
|
Permanent Service | 7/29/2019 | 7/29/2019 | 7/29/2019 | A | PASS |
Tom Saunders
|
|
|
South end service. Phone #: ###-#### Inspection requested via web by Kevin Burke... p/s u/g new ok 13 meters
|
Electrical Rough-In | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Tom Saunders
|
|
|
Last six units on south end Phone #: ###-#### Inspection requested via web by Kevin Burke... 101,102,201,202,301,302 units ok to cover
|
Electrical Rough-In | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Tom Saunders
|
|
|
3rd 6 units from north Phone #: ###-#### Inspection requested via web by Kevin Burke...ok to cover units 103,104,203,204,303,304
|
Electrical Rough-In | 6/23/2019 | 6/24/2019 | 6/24/2019 | A | PASS |
Tom Saunders
|
|
|
2nd 6 units Phone #: ###-#### Inspection requested via web by Kevin Burke.... units 105,106,205,206,305,306...ok to cover
|
Permanent Service | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | PASS |
Tom Saunders
|
|
|
North end service... p/s u/g new ok 7 meters
|
Rough-In Permanent Service | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Tom Saunders
|
|
|
1st six of north end Phone #: ###-#### Inspection requested via web by Kevin Burke... Units 107,108, 207, 208, 307, 308 service NR scheduled inspection for next day
|