Final | 8/27/2019 | 8/28/2019 | 8/28/2019 | P | PASS |
Mark Moncarr
|
|
|
Please call Nick Kelly Phone #: ###-#### Inspection requested via web by Kevin Perez Ok final. Reception desk main level, and island area in basement are completed.
|
Final | 8/16/2019 | 8/19/2019 | 8/19/2019 | P | PART |
Mark Moncarr
|
|
|
Please call Nick Phone #: ###-#### Inspection requested via web by Kevin Perez Ok for furniture move in. Everything for the most part is complelted. A few lights are not installed but are safed off. Check up counter GFI locations, and the same for the basement area.
|
Electrical Rough-In | 8/1/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Ok cover 2 ceilings N side and 1 room center upper level.Basement 3 spaces on E side ceilings, and 2 N end.
|
Electrical Rough-In | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | PASS |
Mark Moncarr
|
|
|
Inspect walls for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Ok cover walls lower level. S and N ends are going to be surface mounted.
|
Electrical Rough-In | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Mark Moncarr
|
|
|
Inspect walls for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Ok cover N and S walls of support room on S side of building.
|
Electrical Rough-In | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Mark Moncarr
|
|
|
Please call Nick Phone #: ###-#### Inspection requested via web by Kevin Perez Ok cover outside wall on bathrooms. Entrance area break room, center room, and all rooms on N side.
|