Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberELE19-02348
StatusFinaled
Name PRIORITY ELECTRIC
Site Address 55 N ALLUMBAUGH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
New: Power for security, lighting, service, and elevators. Building #2
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final3/20/20203/20/20203/20/2020PPASS
DetailsTom Saunders
job complete...corrections made...elevator permit pulled...ok to final
Final3/20/20203/20/20203/20/2020PCANC
DetailsTom Saunders
Final for building #2 Phone #: ###-#### Inspection requested via web by Tom Jenkins...
cancelled wrong inspection...rescheduled
Final3/18/20203/18/20203/18/2020APART
DetailsTom Saunders
Phone #: ###-#### Inspection requested via web by Tom Jenkins...interior of 1st and 2nd floor ok...panels need labelling and outside disconnects need circuit labelling...elevator permit needs pulled before will close out permit
Permanent Service1/7/20201/7/20201/7/2020PPASS
DetailsTom Saunders
Phone #: ###-#### Inspection requested via web by Tom Jenkins...
p/s u/g new/relocation ok...service for new buildings and existing building meter pac
Permanent Service12/31/20191/2/20201/2/2020ACANC
DetailsTom Saunders
Phone #: ###-#### call Dale first thing in morning to make sure AFC labelling received. Inspection requested via web by Tom Jenkins...
AFC labell and info from ID power still not available
Permanent Service12/30/201912/31/201912/31/2019ANR
DetailsTom Saunders
Phone #: ###-#### Inspection requested via web by Tom Jenkins...AFC label required before energized
Electrical Rough-In11/14/201911/14/201911/14/2019PPASS
DetailsTom Saunders
Phone #: ###-#### Inspection requested via web by Tom Jenkins...ok to pour concrete around road grade junction box used as feed thru to move panel accross hallway
Electrical Rough-In8/16/20198/19/20198/19/2019APASS
DetailsTom Saunders
We need an underground inspection please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins...feeds to building from transformer and feeds from main building to other building
Electrical Rough-In7/8/20197/8/20197/8/2019APASS
DetailsTom Saunders
We need an underground inspection for in the slab work. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins...
UG ok to cover
Electrical Rough-In6/26/20196/26/20196/26/2019PPASS
DetailsTom Saunders
Uffer inspection Phone #: ###-#### Inspection requested via web by Tom Jenkins...
bare copper...ok to cover