Final | 8/19/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Tom Saunders
|
|
|
verify breaker labelling and fuse size for charging stations...Rob ###-####.... fuses reduced to MOP nameplate and breakers labelled...ok to final
|
Final | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | NR |
Tom Saunders
|
|
|
Contact: Rob Lawrence Phone #: ###-#### Inspection requested via web by Deb Gooden... rescheduled next day for PM
|
Electrical Rough-In | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | PASS |
Tom Saunders
|
|
|
Contact: Brian Gee.... underground inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden...ok to cvr
|
Electrical Rough-In | 7/11/2019 | 7/15/2019 | 7/15/2019 | A | NR |
Tom Saunders
|
|
|
Contact: Brian Gee... AM underground inspection please Phone #: ###-#### Inspection requested via web by Deb Gooden... contractor will reschedule for next day
|
Conference | 7/11/2019 | 7/12/2019 | 7/12/2019 | P | DONE |
James Ady
|
|
|
Contact: Brian Gee Phone #: ###-#### Inspection requested via web by Deb Gooden Discussed early AM saw cut behind building in a high traffic area. Will make 1st stop 7/15/19 to see if ready. Photos will be ok if time gets tight.
|