Final | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Mark Moncarr
|
|
|
Ok final. No other work done.
|
Permanent Service | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PASS |
Mark Moncarr
|
|
|
Idaho power is shutting off at 7;00 AM, removing old burned up panel and installing new, should be ready for inspection about 10:00 am ish. Adding 2 new circuits in garage also. Phone #: ###-#### Inspection requested via web by Kurt Carlson Tied to existing ufer for GEC. p/s u/g rec ok
|
Permanent Service | 7/1/2019 | 7/2/2019 | 7/1/2019 | P | CANC |
Tom Saunders
|
|
|
Breakers had melted down, damaging busing in the panel, new 200 amp panel tp be installed, Idaho power to shut off power. Inspection required before turn on. 2 additional circuits will be installed at time of panel change out. Should be ready for inspection by 12:30 Phone #: ###-#### >> Inspection requested via web by Kurt Carlson Inspection cancelled from web by: Kurt Carlson
|