Final | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Dan Cox... ok to final
|
Rough-In Permanent Service | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | CANC |
Daryl DeGrange
|
|
|
Office area ceiling inspection before they drop tile. Phone #: ###-#### Inspection requested via web by Dan Cox changed inspection request to r/i only
|
Electrical Rough-In | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PASS |
Daryl DeGrange
|
|
|
Office area ceiling inspection before they drop tile. Phone #: ###-#### Inspection requested via web by Dan Cox Rough-in ok cover ceiling grid
|
Permanent Service | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Tom Saunders
|
|
|
Energize Service Main Phone #: ###-#### Inspection requested via web by Dan Cox... testing and labelling...AFC report plac mounted by final p/s u/g new ok
|
Electrical Rough-In | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Tom Saunders
|
|
|
Heat Tape East Entrance Phone #: ###-#### Inspection requested via web by Dan Cox... ok to pour concrete
|
Conference | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Tom Saunders
|
|
|
MCC Phone #: ###-#### Inspection requested via web by Dan Cox... discussed service adjustments...needs to go back to city for approval...no stamp on plans adjustable breaker and wiring for it, lockability, and access to breaker AFC label and GFCI breaker testing-2 breakers 1000A and 1600A
|
Electrical Rough-In | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PASS |
Tom Saunders
|
|
|
Underground ; office rough in. Phone #: ###-#### Inspection requested via web by Dan Cox.. underground outside East end building and office walls ok to cover
|
Electrical Rough-In | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Tom Saunders
|
|
|
Underground conduits for parking lot. Phone #: ###-#### Inspection requested via web by Dan Cox....ok to cover
|
Electrical Rough-In | 8/19/2019 | 8/19/2019 | 8/19/2019 | A | CANC |
Tom Saunders
|
|
|
Porte Cochere Rough-in Phone #: ###-#### Inspection requested via web by Dan Cox... wrong permit
|
Electrical Rough-In | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Tom Saunders
|
|
|
Under slab Phone #: ###-#### Inspection requested via web by Dan Cox...electrical rm underground...discussed job and requirements... ok'ed wiring methods discussed
|
Electrical Rough-In | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | PASS |
Tom Saunders
|
|
|
UFER ground inspection Phone #: ###-#### Inspection requested via web by Dan Cox.. bare copper uffer ground ok to cover
|