Final | 2/6/2020 | 2/7/2020 | 2/7/2020 | P | PART |
James Ady
|
|
|
Final for building #2. Early PM please. Thank you Phone #: ###-#### Inspection requested via web by Stuart Welton Partial final only still have heater to install
|
Permanent Service | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
James Ady
|
|
|
Service inspection Building #2 Phone #: ###-#### Inspection requested via web by Stuart Welton p/s u/g n ok
|
Electrical Rough-In | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
James Ady
|
|
|
Electrical rough in please. Phone #: ###-#### Inspection requested via web by Stuart Welton 5 units only rough in ok
|
Electrical Rough-In | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PASS |
Daryl DeGrange
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Stuart Welton Building #1C Rough-in ok cover underground service feeders conduits
|
Electrical Rough-In | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PASS |
James Ady
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Stuart Welton Underground from main service to sub panles along footing only ok to cover
|