Electrical Rough-In | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Galban Service, mechanical room rough in ok. Contractor will install J box where a/c conduit leaves crawl space and transition to THWN.
|
Permanent Service | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Galban Contractor will install bushing on sub panel feed as per 300.4G p/s o/h n ok
|
Conference | 8/15/2019 | 8/19/2019 | 8/19/2019 | A | DONE |
Eric Story
|
|
|
Mark Phone #: ###-#### Discussed service change options, contractor will intercept USE cable ran from neighbors yard and turn up to a main discconnect due to all wires are un-fused ran in crawl.
|