Final | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Rock A. Hudson
|
|
|
Darryl said the ETL sticker checked out okay Phone #: ###-#### Inspection requested via web by Keith Chetta No card posted. As per Daryl DeGrange listing OK. Final ok
|
Final | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PART |
Rock A. Hudson
|
|
|
Inspection status from yesterday: Non-approved wiring methods in storage room, open junction box, no all receptacles in service-bay have GFCI protection, Waiting for Paint booth ETL listing tag authenticity.
All of the above code violations have been addressed. Just waiting for ETL authenticity Phone #: ###-#### Inspection requested via web by Keith Chetta Listing of paint booth still needs condirmed. TCO for rest of building ok No card posted
|
Final | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | FAIL |
Daryl DeGrange
|
|
|
Phone #: ###-#### Inspection requested via web by Keith Chetta Non-approved wiring methods in storage room, open junction box, no all receptacles in service-bay have GFCI protection, Waiting for Paint booth ETL listing tag authenticity
|
Final | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | NR |
Daryl DeGrange
|
|
|
Everything except for the spray booth, still waiting for the air switches Phone #: ###-#### Inspection requested via web by Keith Chetta storage room not complete and ready partial final
|
Final | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | FAIL |
Daryl DeGrange
|
|
|
Would like to get a general Electricial final for the building with exception to the paint booth. Still waiting for some solenoid air switches and fire suppression system Phone #: ###-#### Inspection requested via web by Keith Chetta NEC516.4 Area Classification. Compressor branch circuit and light switch installed in Class 1 Division 1 hazardous locations, designated paint storage area
|
Conference | 8/6/2019 | 8/7/2019 | 8/7/2019 | A | PASS |
Daryl DeGrange
|
|
|
I would like to schedule a conference early morning with Inspector Darrell concerning paint booth. Steve Meredith electrical contractor and Manny Mangec general contractor will both be in attendance, thank you Phone #: ###-#### Inspection requested via web by Keith Chetta Discussed NEC 110.3 listing and labeling of equipment, and requirements of Article 516(D)(5)
|
Conference | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | DONE |
Daryl DeGrange
|
|
|
Would like to have a consultation with inspector Daryl about a commercial paint booth Phone #: ###-#### Inspection requested via web by Keith Chetta Discussed with Electrical contractor requirements of NEC 110.3 Listing and Labling of spray booth and spray booth equipment through third party testing company or an Electrical Engineer signing off and giving area classification. Wiring methods compliant with NEC Article 516
|
Electrical Rough-In | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Mark Moncarr
|
|
|
Bathroom roughin , electrician will be on site or close by. Please call if I’m not there to let you in Phone #: ###-#### Inspection requested via web by Keith Chetta Ok cover bathroom only
|