Final | 10/8/2019 | 10/9/2019 | 10/9/2019 | A | PASS |
Tom Saunders
|
|
|
Please call Matt Phone #: ###-#### Inspection requested via web by Kevin Perez... kitchen and new panels ok to final cooler/condensor fix not inspected 2nd permit will need pulled for plan MOD#1 when work starts
|
Final | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | CANC |
Tom Saunders
|
|
|
Contact Mike Garcia for access ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Cloud....building permit under review ...revised plans needed on jobsite for work verification
|
Conference | 10/1/2019 | 10/1/2019 | 10/1/2019 | A | PASS |
Tom Saunders
|
|
|
Contact Matt for access ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Cloud....discussed requirements for final inspection...grounding verification for new panels, labelling panels and devices, and GFCI protection in all areas
|
Electrical Rough-In | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud... ok to cover...new furred out wall, underground pipe fix, and kitchen area ceiling excluding ceiling at back entry and halls...need future inspections
|