Final | 7/3/2020 | 7/6/2020 | 7/6/2020 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Sabrina McCleve Addition final ok
|
Electrical Rough-In | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
James Ady
|
|
|
Sabrina *screened* (if picture inspection being requested) Phone #: ###-#### 1 hallway recep (virtual inspection) rough in ok
|
Electrical Rough-In | 3/28/2020 | 3/30/2020 | 3/30/2020 | P | PASS |
James Ady
|
|
|
Heated floor rough in Phone #: ###-#### Inspection requested via web by Sabrina McCleve Master floor heat only ok to cover
|
Electrical Rough-In | 2/8/2020 | 2/10/2020 | 2/10/2020 | A | PASS |
James Ady
|
|
|
As per our discussion at previous inspection, everything is bonded, switches and plugs installed but not buttoned up. Phone #: ###-#### Inspection requested via web by Sabrina McCleve Device grounding pig tails ok
|
Electrical Rough-In | 9/10/2019 | 9/10/2019 | 9/10/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Sabrina McCleve Need to pig tail Grounding conductors in all switches and call for rough in inspection. Not holding up project at this time. Rough in ok to cover Master bed/bath, Closet, Laundry room and play room
|
Conference | 8/20/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Sabrina McCleve Discussed wiring of addition, all codes items mentioned and owner is very capable of completing project...
|