Final | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
James Ady
|
|
|
EPD breaker installed for roof heat Kitchen/pantry outlets energized Phone #: ###-#### Inspection requested via web by Heath Thomas Corrections made final ok
|
Final | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | FAIL |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas 426.28 Ground fault protection of equipment shall be provided for Fixed electric snow melting equipment. 210.63 Service recep needed within 25ft of minisplit and on the same level. 110.3 Counter receps to the right of kitchen sink dead. Missing panel cover screws.
|
Electrical Rough-In | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas rough in ok
|
Rough-In Permanent Service | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | CANC |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas
|
Electrical Rough-In | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PART |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas Partial only OK to foam seal only. Need misc mud rings installed through out house
|
Permanent Service | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Heath Thomas Back fill will be brought in to ensure a 6ft 7in max breaker hieght on main. p/s u/g n ok
|
Electrical Rough-In | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PASS |
James Ady
|
|
|
PVC conduit and floor boxes for 6 in slab floor receptacles. Phone #: ###-#### Inspection requested via web by Heath Thomas Under slab ok to cover
|