Final | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Mark Moncarr
|
|
|
Job Permit Pack will be left onsite taped to inverter. Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok final. Labels present.
|
Electrical Rough-In | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PASS |
Mark Moncarr
|
|
|
We will be onsite at 9am with the equipment to view UL listings Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok cover. Verified listings.
|
Electrical Rough-In | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Mark Moncarr
|
|
|
Roughed in for solar on roof. Roughed in EMT from roof down to future surface mount inverter location. Phone #: ###-#### Inspection requested via web by Jesse Simpson Ok cover EMT for solar.
|