Final | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Rock A. Hudson
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Joseph Yergensen Final ok
|
Electrical Rough-In | 9/8/2019 | 9/9/2019 | 9/9/2019 | A | PASS |
Rock A. Hudson
|
|
|
I will be on site at 8 am to meet with inspector. Will have materials on ground to verify UL listings and materials used. Thanks Phone #: ###-#### Inspection requested via web by Joseph Yergensen Listings confirmed, rough in ok
|
Final | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | FAIL |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Joseph Yergensen....
Boise city ordinance requires a rough inspection of material before installation or final...material completely installed...material shall be removed to ground level for inspection and UL verification
|