Final | 10/18/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
James Ady
|
|
|
Homeowner has plans and permit with her. Phone #: ###-#### Inspection requested via web by Ashley Lanham Final ok
|
Electrical Rough-In | 9/11/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Tom Saunders
|
|
|
We will be starting the install in the morning, so if you could do rough inspection late morning, we will be further along in the install. Phone #: ###-#### Inspection requested via web by Ashley Lanham... UL listing verified on material
discussed scope of job with onsite journeyman..will be backfeeding from subpanel-electrician will do load calc on subpanel for house, verify sub feed SER is rated to carry 125% of load, and electrician is required to be at FINAL to verify information.
|
Electrical Rough-In | 9/9/2019 | 9/12/2019 | 9/11/2019 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ashley Lanham Inspection cancelled from web by: Ashley Lanham
|
Electrical Rough-In | 9/9/2019 | 9/10/2019 | 9/9/2019 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ashley Lanham Inspection cancelled from web by: Ashley Lanham
|