Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PASS |
Tom Saunders
|
|
|
Please call with questions or concerns. Phone #: ###-#### Inspection requested via web by Stuart Welton...ok to final...all rework and demo in building complete...new lighting areas and added recps complete
|
Electrical Rough-In | 12/3/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Tom Saunders
|
|
|
Ceiling cover inspection. Phone #: ###-#### Inspection requested via web by Stuart Welton.. grid ok to cover
|
Electrical Rough-In | 11/18/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
Tom Saunders
|
|
|
Partial - Entry breakroom. Phone #: ###-#### Inspection requested via web by Stuart Welton... ok to cover...breakroom wall and entry ceiling
|
Electrical Rough-In | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Rock A. Hudson
|
|
|
Electrical rough-in AM please Phone #: ###-#### Inspection requested via web by Stuart Welton Building permit is under review. Unable to inspect until permit is issued.
|