Final | 4/24/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Mark Moncarr
|
|
|
Job site contact is Steve Nuxoll ###-####
THANK YOU ; HAVE A NICE DAY! Phone #: ###-#### Inspection requested via web by JENNY EMEL Ok final. Signed cards on site.
|
Final | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PART |
Tom Saunders
|
|
|
Please contact Steve Nuxoll @ ###-#### upon arrival on site
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL...upstairs complete-1 phone booth light left...dwn stairs offices ok...panels...conference rm
|
Electrical Rough-In | 4/16/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Tom Saunders
|
|
|
Please contact Steve Nuxoll @ ###-#### upon arrival on site
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL...ok to cover counter recps
|
Electrical Rough-In | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Eric Story
|
|
|
Ceiling rough in inspection - please see steve Nuxoll for location Phone #: ###-#### Inspection requested via web by JENNY EMEL 2nd floor west offices ok to cover ceiling
|
Electrical Rough-In | 3/20/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Tom Saunders
|
|
|
Ceiling inspection. Please see Steve Nuxoll for locations Phone #: ###-#### Inspection requested via web by JENNY EMEL...2nd floor North and South offices ok to cover
|
Electrical Rough-In | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PASS |
Tom Saunders
|
|
|
Ceiling rough in inspection
Steve Is the electrician on site
Thank you and stay safe Phone #: ###-#### Inspection requested via web by JENNY EMEL...ok to cover grid 1st floor and 2nd floor west stairwell ok
|
Electrical Rough-In | 3/4/2020 | 3/4/2020 | 3/4/2020 | A | PASS |
Eric Story
|
|
|
Ceiling Inspection - Please contact Steve Nuxoll @ ###-#### with any questions. Thank you ; have a great day! Phone #: ###-#### Inspection requested via web by JENNY EMEL 2nd floor cloud ok to cover
|
Electrical Rough-In | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Tom Saunders
|
|
|
Steve Nuxoll is electrician on site
Thank you and have a wonderful day! Phone #: ###-#### Inspection requested via web by JENNY EMEL... ok to cover...1st floor cloud and exterior canopies x 2...main panel inside visual of connections
|
Permanent Service | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
James Ady
|
|
|
BUTCH GALE IS ELECTRICIAN ON SITE
Thank you ; have a great afternoon! Phone #: ###-#### Inspection requested via web by JENNY EMEL Available fault current 16.8K Will schedule Service rough in before energizing service to check conduits and Sub panel feeder terminations. p/s u/g n ok
|
Electrical Rough-In | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Tom Saunders
|
|
|
Electrician on site is Steve Nuxoll
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL..rescheduled from day before...upstairs walls and hard lids ok to cover
|
Electrical Rough-In | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | CANC |
Tom Saunders
|
|
|
Electrician on site is Steve Nuxoll
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL...rescheduled to next day AM ...contractor requested not ready
|
Electrical Rough-In | 1/20/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Tom Saunders
|
|
|
Thank you and have a great day
Electrician on site is steve nuxoll Phone #: ###-#### Inspection requested via web by JENNY EMEL.. 1st floor East side tenant space walls and needed hard lids
|
Electrical Rough-In | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | PASS |
James Ady
|
|
|
POLE BASE INSPECTION
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL 3 pole bases along E end of parking lot ok to cover. (Poles will be fed from building branch circuits. no cage bonding shown on print.)
|
Electrical Rough-In | 10/17/2019 | 10/17/2019 | 10/17/2019 | A | PASS |
Tom Saunders
|
|
|
Underground inspection - contact Butch with any questions or concerns.
Have a lovely day! Phone #: ###-#### Inspection requested via web by JENNY EMEL...slab underground ok to cover
|
Electrical Rough-In | 10/9/2019 | 10/9/2019 | 10/9/2019 | P | PASS |
Tom Saunders
|
|
|
Underground Inspection for Interior of building. Please call Steve Nuxoll @ ###-#### with any questions.
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL...power feeds,site lighting, and fiber pipes...south side of building...ok to cover
|
Electrical Rough-In | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PASS |
Tom Saunders
|
|
|
Ufferground inspection. Please call Steve Nuxoll with any questions ###-####
Thank you ; have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL... copper wire attached to rebar...ok to cover
|