Final | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Occ card signed-Final ok
|
Conference | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | DONE |
Eric Story
|
|
|
Need to discuss future fuel station conduit runs. Conduits are 30" deep but were back filled without being inspected to keep parking lot open. Phone #: ###-#### Inspection requested via web by Jeremy Cloud Depth of conduit ran verified by pictures, work to be done by others.....
|
Final | 5/4/2020 | 5/5/2020 | 5/5/2020 | P | PART |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Offices only ok to occupy
|
Electrical Rough-In | 5/5/2020 | 5/5/2020 | 5/5/2020 | P | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud 110.26 Work space clearences on Disc in bay with balllards directly in front of Disc
|
Electrical Rough-In | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud 314.28- Minimum junction box for feed from main to transformer disconnect shall be 8 times largest conduit. 2"x 8=16" minimum. 12"x 12" installed. Walked interior lighting and found 2 open boxes which feed roof top fans. Interior structure grid rough in ok cover and transformer bonding rough in ok cover.
|
Electrical Rough-In | 1/31/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Approved plans on-site U/G for future data and walls in offices in shipping area ok to cover
|
Electrical Rough-In | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Eric Story
|
|
|
Inspect underground for cover. Nick Kelly ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Cloud U/G front area and pole bases ok to cover@pour
|
Electrical Rough-In | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Eric Story
|
|
|
Inspect underground for cover. Nick Kelly ###-#### Phone #: ###-#### Inspection requested via web by Jeremy Cloud South end of parking lot ok to cover
|
Electrical Rough-In | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | FAIL |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Need BLD issued
|
Electrical Rough-In | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud Access far right of building on dirt road. U/G as marked on print for east side ok to cover
|