Final | 8/11/2020 | 8/11/2020 | 8/11/2020 | A | PART |
Tom Saunders
|
|
|
fire riser room, fire panel, heat trace and control panel, breezeways, roof. Phone #: ###-#### Inspection requested via web by Todd Hall...
building ok for occupency...permit left open for carports
|
Final | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | PART |
Tom Saunders
|
|
|
1st and 2nd floor apts, rooftop units, fire rm, and all exterior...
all roomscomplete fire riser rm, rooftop, and house panel need still completed for full final
|
Final | 8/7/2020 | 8/7/2020 | 8/7/2020 | A | PART |
Tom Saunders
|
|
|
final for all units (as many as can be inspected today) Phone #: ###-#### Inspection requested via web by Todd Hall...
3rd and 4th floors only...ok
|
Electrical Rough-In | 5/29/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Tom Saunders
|
|
|
1st and 2nd floor ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall...ok to cover
|
Electrical Rough-In | 5/20/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Tom Saunders
|
|
|
ceiling drops 3rd and 4th floor Phone #: ###-#### Inspection requested via web by Todd Hall... drops ok to cover
|
Electrical Rough-In | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Tom Saunders
|
|
|
bldg K heat trace locations, breezeways and shaft liners Phone #: ###-#### Inspection requested via web by Todd Hall..complete...ok to cover
|
Electrical Rough-In | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Tom Saunders
|
|
|
breezeway and landing ceilings (except heat tape locations) Phone #: ###-#### Inspection requested via web by Todd Hall... all floor breezeways ok to cover minus heat tape area and junction box
|
Rough-In Permanent Service | 3/20/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Tom Saunders
|
|
|
rough in for 1st and 2nd floor units visual for service gear...call Ben to open up... rough in for 1st floor and 2nd floor units p/s u/g new ok...17 meters needed
|
Rough-In Permanent Service | 3/19/2020 | 3/20/2020 | 3/20/2020 | P | PASS |
Tom Saunders
|
|
|
Rough in complete except for breezeway ceilings. permanent service Phone #: ###-#### Inspection requested via web by Todd Hall... 4th and 3rd floor units and 4th floor metal fir downs in breezeways 2nd and final warning of foam sealing before inspection...general foreman was made aware of and understands work will be removed if happens again...boise city ordinance
|
Conference | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | DONE |
Tom Saunders
|
|
|
Bldg K conference for ACs on roof. Contact Ben ###-#### Phone #: ###-#### Inspection requested via web by Todd Hall...discussed wiring of A/Cs on rooftop...disconnect/switch location-not OCPD-access requirement and wiring to ea individual A/C accross floor of roof not using A/C as support locations
|
Electrical Rough-In | 10/2/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Tom Saunders
|
|
|
underslab, yes, underslab!! for kitchen islands. Contact Todd ###-#### Phone #: ###-#### Inspection requested via web by Todd Hall...quality work...amazing job...your guys are super...ok to cover
|