Final | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PASS |
Tom Saunders
|
|
|
Rigo is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen... job complete ok to final
|
Final | 5/26/2020 | 5/28/2020 | 5/28/2020 | A | PART |
Eric Story
|
|
|
Please call Von 1/2 prior to arrival. Thanks Phone #: ###-#### Inspection requested via web by Buster Bowen AFC calc not posted Label breakers to according panels Install x-ray equipment
|
Electrical Rough-In | 4/2/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Tom Saunders
|
|
|
Ceiling Cover. Rigo is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen...remaining grid ok to cover
|
Permanent Service | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Tom Saunders
|
|
|
Rigo is the onsite contact Phone #: ###-#### Inspection requested via web by Buster Bowen... AFC label verified by ID Power email label installed by final p/s u/g new ok
|
Electrical Rough-In | 3/23/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Tom Saunders
|
|
|
Above Ceiling cover. Rigo is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen..grid ok- exterior perimeter exam rooms, front reception E and W sides, and reception desk area only
|
Electrical Rough-In | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | PASS |
Tom Saunders
|
|
|
UG cover. Rigo is the onsite contact. Thanks Phone #: ###-#### Inspection requested via web by Buster Bowen...perimeter building lighting and service feeds...ok to cover
|
Electrical Rough-In | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Tom Saunders
|
|
|
UG cover. Rigo is the onsite contact Phone #: ###-#### Inspection requested via web by Buster Bowen...ok to cover...parking lot lighting
|
Electrical Rough-In | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | CANC |
Eric Story
|
|
|
Canopy cover. Toby is the contact. Please note there is not access to site between 8-8:45am. Phone #: ###-#### Inspection requested via web by Buster Bowen Wrong permit called in
|
Electrical Rough-In | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Rock A. Hudson
|
|
|
Wall cover. Von is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen Unable to confirm #10 minimum bond to panel board required by 517.14. Asked wireman and he stated provisions have been provided to install it. X-ray room walls rough in ok cover
|
Electrical Rough-In | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Tom Saunders
|
|
|
Ceiling cover in front lobby. Rigo is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen... lobby/reception hard lid ok to cover..cans and pendants
|
Electrical Rough-In | 1/22/2020 | 1/22/2020 | 1/22/2020 | A | PASS |
Tom Saunders
|
|
|
Wall cover. Rigo is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen...wall cover complete
|
Electrical Rough-In | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | PASS |
Tom Saunders
|
|
|
Wall Cover. Rigo is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen.... wall cover...14 exam rms, all exterior, and fire riser rm
|
Electrical Rough-In | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Tom Saunders
|
|
|
Von. Underground floor box. Phone #: ###-#### Inspection requested via web by Sean DeLacy...slab ok to pour
|
Electrical Rough-In | 11/22/2019 | 11/25/2019 | 11/25/2019 | A | PASS |
Eric Story
|
|
|
UG cover. Von is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen U/G in slab ok to cover
|
Electrical Rough-In | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Tom Saunders
|
|
|
Ufer inspection. Von is the contact. Phone #: ###-#### Inspection requested via web by Buster Bowen...ok... poured before viewing...images from contractor and general
|