Electrical Rough-In | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | PASS |
Rock A. Hudson
|
|
|
Rough in inspection for vestibule and reception walls and ceilings. Show window areas above mullions. Raised seating wood frame walls. Phone #: ###-#### Inspection requested via web by John Mittleider Areas noted rough in ok cover.
|
Conference | 3/10/2020 | 3/11/2020 | 3/11/2020 | A | PASS |
Rock A. Hudson
|
|
|
Discuss whether a drain pan will be necessary over garage panel boards. Phone #: ###-#### Inspection requested via web by John Mittleider Discussed requirement for drip protection of panel boards for new equipment located in baseement. Nearest pipe to dedicated electrical space is a non-pressurized drain line. Minimal protection required for drip type leak, spray hazard not present in this line.
|
Electrical Rough-In | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Eric Story
|
|
|
Cover inspection for bar ceiling, hostess ceiling, bar dining wall and drop ceiling. Review acceptability of drain pan over garage panels. Phone #: ###-#### Inspection requested via web by John Mittleider Areas as noted on print ok to cover *looked at area in garage for work clearences with water pipes over panelboard a conference will be requested as a pan above panelbord will approach work clearences as per 110.26 needing 6' above
|
Electrical Rough-In | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Eric Story
|
|
|
Rough in inspection for restrooms and banquet rooms walls and ceilings. Inspect ceiling of lower soffit surrounding Upper Dining area. Phone #: ###-#### Inspection requested via web by John Mittleider Areas as noted on print ok to cover
|
Electrical Rough-In | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Rock A. Hudson
|
|
|
Wall rough in inspection. North of column A-D. West of serving counter wall. Column A-4. Phone #: ###-#### Inspection requested via web by John Mittleider Areas noted on contractor print walls only rough in ok cover.
|
Electrical Rough-In | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | PASS |
Rock A. Hudson
|
|
|
Inspect raceways under slab in dining rooms , restaurant and bar areas. Phone #: ###-#### Inspection requested via web by John Mittleider Areas noted plus private dining under slab rough in ok cover.
|
Electrical Rough-In | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Rock A. Hudson
|
|
|
Under slab raceways in kitchen, coffee bar, restrooms, private dining areas Phone #: ###-#### Inspection requested via web by John Mittleider Private dining not ready the rest listed underslab rough in ok cover.
|
Electrical Rough-In | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PART |
Rock A. Hudson
|
|
|
Wall inspection for 24” cement board rips from structural slab. Confirm requirements for show window receptacles. Phone #: ###-#### Inspection requested via web by John Mittleider Bottom 24" of walls as noted on contractor print for floor build up rough in ok cover.
|