Final | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PASS |
Tom Saunders
|
|
|
remaining units for final...building units and area lighting off building complete...ok to final
|
Final | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PART |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Hall...
Units ok..306, 205, 206,105,106,103,204 all units water heaters need addressed..site journeyman aware of units need reinspect...104,203 units not done...305, 304, 303, 302,301,202,201,102,101
|
Electrical Rough-In | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PASS |
Tom Saunders
|
|
|
pole bases (2) Phone #: ###-#### Inspection requested via web by Todd Hall.. parking lot pole bases ok to pour
|
Electrical Rough-In | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | NR |
Tom Saunders
|
|
|
pole base inspection Phone #: ###-#### Inspection requested via web by Todd Hall.. installation not complete
|
Electrical Rough-In | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Tom Saunders
|
|
|
ceiling drops in 12 East end units Phone #: ###-#### Inspection requested via web by Todd Hall...all remaining ceiling drops and furnaces ok to cover
|
Electrical Rough-In | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Tom Saunders
|
|
|
ceiling drops building 12 Phone #: ###-#### Inspection requested via web by Todd Hall... drops and furnaces all units...ok to cover
|
Electrical Rough-In | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | CANC |
Tom Saunders
|
|
|
Ceiling drops Phone #: ###-#### Inspection requested via web by Todd Hall... inspection done Fri 2/7/20
|
Electrical Rough-In | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Tom Saunders
|
|
|
bldg 12 ceiling drops...west end 6 units ok to cover
|
Electrical Rough-In | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Tom Saunders
|
|
|
rough for units: K105,205,305,106,206,306 and re-inspect of kitchen ''wing'' walls at peninsulas of previous 12 units. Call Todd if any questions. Phone #: ###-#### Inspection requested via web by Todd Hall... rough-in ok to cover units 105,106,205,206,305,306 reinspect of first 12 units kitchen ok
|
Permanent Service | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Hall.... p/s u/g new ok...19 meters for meter pac
|
Electrical Rough-In | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Tom Saunders
|
|
|
rough in for 12 units K101 thru K104 K201 thru K204 K301 thru K304 Phone #: ###-#### Inspection requested via web by Todd Hall...
rough in ok to cover...101-104, 201-201,301-304 future inspections for drop ceilings and furnace hook up required
|