Final | 11/20/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Rock A. Hudson
|
|
|
Area code 801. Final solar inspection. Plans are on site at the Solaredge inverter. Phone #: ###-#### Inspection requested via web by Ashley Lanham NM cable noted changed to UF. Final ok
|
Electrical Rough-In | 11/18/2019 | 11/20/2019 | 11/20/2019 | A | PASS |
James Ady
|
|
|
Area code 801. Solar Mid Inspection. Phone #: ###-#### Inspection requested via web by Ashley Lanham Listing only. (Note: spoke to contractor about 12-2 romex installed in sealtight leading to a recep in backyard. Will need to be removed before final)
|