Final | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Tom Saunders
|
|
|
contact...chris ###-####...ok to final...sign stubs will be safed off....power for signs is end of contract...future permit will need pulled by others
|
Electrical Rough-In | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bayley Beard... rough in of seating area and walkways ok to cover...future rough inspections required for ceiling piping for special affects equipment and new power feeds to control room
|
Electrical Rough-In | 12/16/2019 | 12/16/2019 | 12/17/2019 | P | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Christy Cheney Called and had Tiffany ELE attached to BLD19-00822. Will be wiring to all staduim seating, new projector, and special effects machines. Discussed if ENT could be used for a low voltage run to dog house. As per 520.5 all wiring methods shall be metal raceway or cable. Non metallic only if contained in a minimum of 2" of concrete. 520.5(A)ex. Refer to artical 640 for audio signal, amplification, and reproduction equipment. Wiring methods requirements from chapters 1 thru 4 ok. DHX sub fed panel, transformer, panel, and a second panel in same area on level 2 rough in ok.
|
Permanent Service | 12/15/2019 | 12/16/2019 | 12/16/2019 | A | CANC |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Christy Cheney Needed rough in inspection
|
Rough-In Permanent Service | 12/12/2019 | 12/13/2019 | 12/13/2019 | A | CANC |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Christy Cheney Wrong building permit attached to this permit. M&M called to inform they had not seen an inspector all day. Will reschedule for Monday.
|