Final | 1/30/2020 | 1/31/2020 | 1/31/2020 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Ashley Rasmussen Solar Array final ok
|
Final | 1/27/2020 | 1/28/2020 | 1/28/2020 | A | NH |
Rock A. Hudson
|
|
|
all labeled up and ready not doing the sub to the garage. Call me with any questions thank you! Phone #: ###-#### Inspection requested via web by Ashley Rasmussen No answer at door. Must have owneor rep from company on site to enter fence back yard.
|
Electrical Rough-In | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
James Ady
|
|
|
May have messed up crew called the historical for inspection forgot to online request. Crew is in area to go remove panels Phone #: ###-#### Inspection requested via web by Ashley Rasmussen Listing only ok. (Discussed conduit to detached garage being used for 240V 30A welder cuircuit. Disc. will be required. also discussed loose EMT connectors) Breaker labeling must be completed before final. Listing ok only
|