Final | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Tom Saunders
|
|
|
Please contact Raul with any questions. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins... surface wiring...conduit and m/c...interior lighting and exterior lighting on buildings
|
Electrical Rough-In | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Rock A. Hudson
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Jenkins North side underground rough in ok cover
|
Electrical Rough-In | 12/31/2019 | 12/31/2019 | 12/31/2019 | P | PASS |
Tom Saunders
|
|
|
We have a uffer that needs an inspection, please. Phone #: ###-#### Inspection requested via web by Tom Jenkins..ok to cover...stranded copper wire for circuit connection
|
Electrical Rough-In | 12/30/2019 | 12/31/2019 | 12/31/2019 | A | NR |
Tom Saunders
|
|
|
We need a uffer inspection for the second pad, please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins... no uffer installed reschedule when ready!!!
|
Electrical Rough-In | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Tom Saunders
|
|
|
We need a uffer inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins...uffer ground ok to cover...bare copper attached to rebar for branch circuit to storage building
|
Electrical Rough-In | 12/17/2019 | 12/18/2019 | 12/18/2019 | P | CANC |
Tom Saunders
|
|
|
We need a uffer inspection please. Thank you. Phone #: ###-#### Inspection requested via web by Tom Jenkins...contractor notified rebar did not get installed...inspection scheduled for next day
|
Electrical Rough-In | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | CANC |
James Ady
|
|
|
Uffer Ground Phone #: ###-#### >> Inspection requested via web by Tom Jenkins Inspection cancelled from web by: Tom Jenkins
|