Final | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Mark Moncarr
|
|
|
There should be good access for inspection today. Please give me a call if there are any questions or if I should make arrangements to meet you on site. Phone #: ###-#### Inspection requested via web by Casey Fouts Ok final
|
Permanent Service | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PASS |
Mark Moncarr
|
|
|
Ready for inspection Phone #: ###-#### Inspection requested via web by Casey Fouts Where overhead service drop will be attached at new service location, as close as the pole is the drop should be easily be 12' over residential property. p/s o/h n ok
|
Permanent Service | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | CANC |
Mark Moncarr
|
|
|
Talked to contractor switched p/s to tomorrow. Wasnt ready. As per contractor.
|
Permanent Service | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | CANC |
Mark Moncarr
|
|
|
Not ready. Rescheduled for 2/21 as per contractor
|
Electrical Rough-In | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | PASS |
Mark Moncarr
|
|
|
Access through Gerard should be available however please call in advance to ensure access. We would also like to add in a permanent service inspection to this property as well. Phone #: ###-#### Inspection requested via web by Casey Fouts Ok cover
|