Final | 5/5/2020 | 5/5/2020 | 5/5/2020 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Ballenger...job complete...meter set..ok to final
|
Permanent Service | 5/4/2020 | 5/5/2020 | 5/5/2020 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Greg Ballenger...service already powered...needed final...scheduled and resulted
|
Rough-In Permanent Service | 4/27/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Tom Saunders
|
|
|
Service change Phone #: ###-#### Inspection requested via web by Greg Ballenger.. temped in do to storm and Idaho Power unable to move service lateral...be moved and reconnected first thing 5/4/20 AM p/s u/g reconnect ok
|
Conference | 4/23/2020 | 4/24/2020 | 4/24/2020 | P | PASS |
Tom Saunders
|
|
|
WIll be changing service out on 5/1. Would like to schedule a Conference Phone #: ###-#### Inspection requested via web by Greg Ballenger.. discussed new service...grounding up dating, refeed existing sub panel-not split bus, fix existing double fed circuits at service now
|