Permanent Service | 7/20/2020 | 7/20/2020 | 7/20/2020 | A | PASS |
James Ady
|
|
|
Changed service from underground to overhead. Call with any questions. Phone #: ###-#### Inspection requested via web by Casey Fouts p/s o/h n ok
|
Permanent Service | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Rock A. Hudson
|
|
|
Please call with any questions. Phone #: ###-#### Inspection requested via web by Casey Fouts p/s u/g n ok
|
Rough-In Permanent Service | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | FAIL |
Rock A. Hudson
|
|
|
Underground conduits for service and new meter pack Phone #: ###-#### Inspection requested via web by Casey Fouts 230.42- Service entrance conductors shall be installed from meter to panel to verify size. 300.5(D)(3)- Service entrance underground conductors18" and deeper shall be marked with warning tape. 300.5(F)- soft backfill shall be installed to protect conduit from large rocks. Contractor called, sand being delivered, tape planned at required 12" above pipe. Will recall when ready.
|