Electrical Rough-In | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Daryl DeGrange
|
|
|
Shawn *screened* Phone #: ###-#### P/S U/G REC OK
|
Electrical Rough-In | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | FAIL |
Daryl DeGrange
|
|
|
Shawn- */Screened*/ Phone #: ###-#### Service conductor terminations not complete,
|
Rough-In Permanent Service | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | NR |
Daryl DeGrange
|
|
|
Idaho Power is set to bring in the 400amp service on Thursday. We have the 400amp meeter main and the 2 x 200 amp disconnects outside ready for inspection. Phone #: ###-#### Inspection requested via web by Shawn Whitaker Not ready for power connection at this time
|
Conference | 6/22/2020 | 6/23/2020 | 6/23/2020 | A | DONE |
Daryl DeGrange
|
|
|
Review over New 400amp service Phone #: ###-#### Inspection requested via web by Shawn Whitaker Discussed with homeowner approved conductors for interior structural wiring, service conductors, service clearances, AFCI protected branch circuits.
|