INSP - Final | 4/2/1996 | 4/3/1996 | 4/3/1996 | A | PASS |
Pat Lass
|
|
|
04/02/96 336 - reinspection final Ok
|
INSP - Final | 4/2/1996 | 4/2/1996 | 4/2/1996 | P | FAIL |
Pat Lass
|
|
|
04/02/96 336 - AFTER 3:00 TODAY Disapproved GFCI Bond steel
|
INSP - Electrical Rough-In | 3/28/1996 | 3/28/1996 | 3/28/1996 | P | PASS |
Pat Lass
|
|
|
03/28/96 336 - CEILING ROUGH R/I Ok ì
|
INSP - Electrical Rough-In | 3/28/1996 | 3/28/1996 | 3/28/1996 | | PASS |
Pat Lass
|
|
|
03/28/96 336 - CEILING ROUGH R/I Ok ì
|
INSP - Electrical Rough-In | 3/28/1996 | 3/28/1996 | 3/28/1996 | | PASS |
Pat Lass
|
|
|
03/28/96 336 - CEILING ROUGH R/I Ok ì
|
INSP - Electrical Rough-In | 3/28/1996 | 3/28/1996 | 3/28/1996 | | PASS |
Pat Lass
|
|
|
03/28/96 336 - CEILING ROUGH R/I Ok ì
|
INSP - Permanent service | 3/12/1996 | 3/13/1996 | 3/13/1996 | A | PASS |
Pat Lass
|
|
|
03/12/96 336 - P/S Ok
|
INSP - Electrical Rough-In | 3/1/1996 | 3/4/1996 | 3/4/1996 | A | PASS |
Pat Lass
|
|
|
03/01/96 336 - COVER ON WALL BY MCDONALD Partial R/I ok
|
INSP - Electrical Rough-In | 2/28/1996 | 2/28/1996 | 2/28/1996 | P | PASS |
Pat Lass
|
|
|
02/28/96 336 - THIS WAS SENT TO JACK IT IS YOURS PAT. Partial R/I Ok
|
INSP - Electrical Rough-In | 2/27/1996 | 2/28/1996 | 2/28/1996 | A | CANC |
Jack Frank
|
|
|
02/27/96 315 - transfered to PLass jf
|
INSP - Electrical Rough-In | 2/16/1996 | 2/16/1996 | 2/16/1996 | P | PASS |
Jack Frank
|
|
|
02/16/96 315 - FIRE WALL 09 ok jf
|
INSP - Electrical Rough-In | 11/28/1995 | 11/29/1995 | 11/29/1995 | A | PASS |
Jack Frank
|
|
|
11/29/95 315 - GROUND WORK IN THE BUILDING 03 ok jf
|
INSP - Ground work | 11/22/1995 | 11/22/1995 | 11/22/1995 | P | PASS |
Jack Frank
|
|
|
11/22/95 315 - SAID THEY NEEDED A R/I ON THE GROUND WORK 03 ok jf
|
INSP - Ground work | 11/14/1995 | 11/15/1995 | 11/15/1995 | A | CANC |
Jack Frank
|
|
|
11/15/95 315 - UNDERGROUND INSPECTION IN TANK AREA NEEDED//ANY MORE INFO done on previous mod.
|