INSP - Final | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | PASS |
Jim Schmer
|
|
|
|
INSP - Final | 12/16/1996 | 12/16/1996 | 12/16/1996 | P | NR |
Jack Frank
|
|
|
12/16/96 315 - no 14 25 only and Tom has alredy given 25 I went out ther Tom had posted it was ok jf
|
INSP - Final | 12/12/1996 | 12/13/1996 | 12/13/1996 | A | FAIL |
|
|
|
couldn't locate lea elect. people to talk about generation corr.
|
INSP - Final | 12/3/1996 | 12/4/1996 | 12/4/1996 | P | FAIL |
|
|
|
TRU-2 unit on roof panel not labeled 384-13 (see t/o - ok)
|
INSP - Temporary occupancy | 12/5/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
NOT A FINAL!!!!! by jms
|
INSP - Temporary occupancy | 12/5/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
|
|
|
NOT A FINAL!!!!! by jms
|
INSP - Final | 11/13/1996 | 11/14/1996 | 11/14/1996 | P | PART |
|
|
|
THEATER AND ATRUIM FINAL --T.O. only--
|
ELE - Partial final | 11/6/1996 | 11/7/1996 | 11/7/1996 | P | PASS |
Jack Frank
|
|
|
11/07/96 315 - FOR KITCHEN ONLY partial 14 ok jf
|
INSP - Final | 10/31/1996 | 10/31/1996 | 10/31/1996 | P | PART |
|
|
|
TEMP OCC--all of the building accept 1) atrium 2) theater and 3) kitchen.--
|
ELE - Partial final | 10/29/1996 | 10/30/1996 | 10/30/1996 | P | PASS |
|
|
|
FIRST FLOOR ONLY
|
INSP - Final | 10/24/1996 | 10/25/1996 | 10/25/1996 | A | PART |
Joe Ray
|
|
|
10/25/96 404 - SECOND FLOOR
|
ELE - Partial final | 10/24/1996 | 10/23/1996 | 10/23/1996 | P | PASS |
|
|
|
area lighting
|
INSP - Electrical Rough-In | 10/18/1996 | 10/18/1996 | 10/18/1996 | P | PASS |
Jack Frank
|
|
|
10/18/96 315 - FOR FIRST FLOOR 09 ok jf
|
INSP - Electrical Rough-In | 10/10/1996 | 10/11/1996 | 10/11/1996 | P | CANC |
|
|
|
CLEARANCE FOR FIRST AND SECOND FLOOR --given to Jack Frank--
|
INSP - Electrical Rough-In | 10/10/1996 | 10/9/1996 | 10/9/1996 | P | PASS |
|
|
|
|
INSP - Electrical Rough-In | 10/3/1996 | 10/3/1996 | 10/3/1996 | A | PASS |
|
|
|
VARIOUS AREAS TALKED TO RICH ABOUT WORKING CLEARANCE MAKE-UP AIR UNITS-332
|
INSP - Electrical Rough-In | 9/30/1996 | 9/30/1996 | 9/30/1996 | P | PASS |
Jack Frank
|
|
|
09/30/96 315 - TCI THEATER BUILDING 09 ok jf
|
INSP - Permanent service | 9/24/1996 | 9/26/1996 | 9/26/1996 | A | PASS |
|
|
|
comm job...tg
|
INSP - Conference | 9/20/1996 | 9/20/1996 | 9/20/1996 | A | PASS |
|
|
|
about lock outs on breakers for heat unit in ceiling.
|
INSP - Conference | 9/16/1996 | 9/16/1996 | 9/16/1996 | A | PASS |
|
|
|
quads 2 & 3 upstairs. spent most of the morning up air units. Pat also spent some time at this location as I asked him to also look at clearence problems.
|
INSP - Electrical Rough-In | 9/9/1996 | 9/9/1996 | 9/9/1996 | P | CANC |
|
|
|
KITCHEN AREA ONLY --Given to Pat Lass--
|
INSP - Electrical Rough-In | 9/6/1996 | 9/6/1996 | 9/6/1996 | A | PASS |
|
|
|
R/I TCI QUADS 1 & 3 FIRST FLOOR-PAT WAS ALSO WITH ME ON THIS INSPECTION OK
|
INSP - Electrical Rough-In | 9/3/1996 | 9/3/1996 | 9/3/1996 | A | PASS |
|
|
|
conduit quad 3 & 4
|
INSP - Electrical Rough-In | 8/27/1996 | 8/27/1996 | 8/27/1996 | P | CANC |
|
|
|
1 floor quad.3
|
INSP - Miscellaneous | 8/21/1996 | 8/20/1996 | 8/20/1996 | P | FAIL |
|
|
|
(110-16 and 110-16-A working clearance - 110-3-A-1 listing of equipment) EMERGENCY GENERATOR - Boise City Elect. Ordinance - 4-5-60-A Approval of Products and Materials.
|
INSP - (Pools) bonding | 8/16/1996 | 8/19/1996 | 8/19/1996 | A | PASS |
|
|
|
FOR FOUNTAIN
|
INSP - Electrical Rough-In | 8/14/1996 | 8/14/1996 | 8/14/1996 | A | PASS |
|
|
|
Quad 2 & 4 main elect. room
|
INSP - Electrical Rough-In | 8/6/1996 | 8/7/1996 | 8/7/1996 | A | PASS |
|
|
|
Q 2 & 4 ok
|
INSP - Electrical Rough-In | 7/30/1996 | 7/30/1996 | 7/30/1996 | A | PART |
|
|
|
Quads 1,2,3,& 4 Lower OK
|
INSP - Conference | 7/22/1996 | 7/19/1996 | 7/19/1996 | P | PASS |
|
|
|
With Bill of Lea Electric
|
INSP - Electrical Rough-In | 7/16/1996 | 7/18/1996 | 7/18/1996 | A | PART |
|
|
|
1ST FLOOR QUAD 2 1 & 4 - 2nd Floor OK
|
INSP - Electrical Rough-In | 7/12/1996 | 7/15/1996 | 7/15/1996 | | PASS |
|
|
|
|
INSP - Electrical Rough-In | 7/1/1996 | 7/2/1996 | 7/2/1996 | A | PART |
|
|
|
QUAD 2 SECOND FLOOR PARTIAL OK
|
INSP - Ground work | 5/7/1996 | 5/8/1996 | 7/2/1996 | A | CANC |
|
|
|
|
INSP - Electrical Rough-In | 6/26/1996 | 6/26/1996 | 6/26/1996 | P | PASS |
|
|
|
R/I QUAD 1 & 2 PAT LASS ALSO ON THIS INSP.
|
INSP - Electrical Rough-In | 6/24/1996 | 6/21/1996 | 6/21/1996 | A | PART |
|
|
|
R/I PARTIAL VARIOUS LOCATIONS
|
INSP - Conference | 6/19/1996 | 6/19/1996 | 6/19/1996 | A | PASS |
Carl Dependahl
|
|
|
332-06/18/96-CONF-LIGHTING FLEX INSTALLATION W/BILL OF LEA ELECTRIC.
|
INSP - Electrical Rough-In | 6/14/1996 | 6/17/1996 | 6/17/1996 | A | PASS |
Joe Ray
|
|
|
|
INSP - Electrical Rough-In | 6/13/1996 | 6/14/1996 | 6/14/1996 | A | PASS |
Joe Ray
|
|
|
|
INSP - Conference | 6/5/1996 | 6/5/1996 | 6/5/1996 | A | PASS |
|
|
|
CONF ELECT ROOM CLEARENCE W/BILL OF LEA ELEC
|
INSP - Electrical Rough-In | 6/4/1996 | 6/4/1996 | 6/4/1996 | P | PASS |
|
|
|
R/I OK CONDUIT TO GENERATER CONF ELECT ROOM
|
INSP - Electrical Rough-In | 5/29/1996 | 5/29/1996 | 5/29/1996 | A | PASS |
|
|
|
QUADE #2 AND OTHER LOCATIONS OK=
|
INSP - Electrical Rough-In | 5/24/1996 | 5/24/1996 | 5/24/1996 | A | PASS |
|
|
|
CONDUIT VARIOUS LOCATIONS OK TCI BLDG
|
INSP - Ground work | 5/7/1996 | 5/8/1996 | 5/8/1996 | A | PASS |
|
|
|
CONDUIT IN BLDG FOR SITE LIGHTING OK
|
INSP - Ground work | 5/3/1996 | 5/6/1996 | 5/6/1996 | A | PASS |
|
|
|
UG CONDUIT AREA LIGHTING .
|
INSP - Ground work | 5/3/1996 | 5/3/1996 | 5/3/1996 | P | CANC |
|
|
|
|
INSP - Ground work | 4/29/1996 | 4/29/1996 | 4/29/1996 | A | PASS |
|
|
|
UNDERGROUND CONDUIT OK
|
INSP - Ground work | 4/17/1996 | 4/18/1996 | 4/18/1996 | A | PASS |
|
|
|
GROUND RING OK
|
INSP - Conference | 4/11/1996 | 4/12/1996 | 4/12/1996 | A | PASS |
|
|
|
CONF WITH LEA ELECT.
|
INSP - Ground work | 4/2/1996 | 4/2/1996 | 4/2/1996 | P | PASS |
|
|
|
UG CONDUIT OK
|