INSP - Final | 2/25/1999 | 2/26/1999 | 2/26/1999 | P | PASS |
Marv Burrus
|
|
|
###-#### steve CORRECTIONS COMPLETED. OK
|
INSP - Final | 2/24/1999 | 2/25/1999 | 2/25/1999 | A | FAIL |
Jack Frank
|
|
|
02/25/99 315 - ###-#### Steve cor. posted 370-17(c) M.B. bath switch 200 reversed polarity upstairs ba called left message
|
INSP - Electrical Rough-In | 2/11/1999 | 2/11/1999 | 2/11/1999 | P | PASS |
Marv Burrus
|
|
|
service reinspection steve ###-#### CONCRETE ENCASED GROUNDING CONDUCTOR; PERM/SVC. OK
|
INSP - Electrical Rough-In | 2/9/1999 | 2/10/1999 | 2/10/1999 | A | PART |
Marv Burrus
|
|
|
02/10/99 403 - ###-#### Steve Grounding inspect CONCRETE ENCASED GROUNDING CONDUCTOR INSPECTION FOR PERM/SVC.
|
INSP - Electrical Rough-In | 1/25/1999 | 1/27/1999 | 1/27/1999 | P | NR |
Jack Frank
|
|
|
01/27/99 315 - steve- ###-#### r/i insp (check U-fer grd.)..trans jms.. fail nr canceled by contractor
|
INSP - Electrical Rough-In | 1/22/1999 | 1/26/1999 | 1/26/1999 | A | PART |
Marv Burrus
|
|
|
01/25/99 403 - steve ###-#### r/i & serv ELE R/I ONLY; SERVICE PANEL NOT GROUNDED. CONTRACTOR WILL RESCHEDULE PER
|