Final | 9/25/2000 | 9/26/2000 | 9/26/2000 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/25/2000 at 15:39:16. Contact: ###-####. remodel completed. 9/26/2000 5:56:20 PM
|
Final | 9/21/2000 | 9/22/2000 | 9/22/2000 | P | CANC |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/21/2000 at 18:05:08. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/22/2000 at 08:39:09.
|
Electrical Rough-In | 9/20/2000 | 9/21/2000 | 9/21/2000 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/20/2000 at 15:11:00. Contact: ###-####. outside lighting; temp. occupancy. 9/21/2000 10:34:53 PM
|
Electrical Rough-In | 9/18/2000 | 9/19/2000 | 9/19/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/18/2000 at 13:49:43. Contact: ###-####. pump/pool room; basement, ele r/i. 9/19/2000 12:44:15 PM
|
Electrical Rough-In | 9/14/2000 | 9/14/2000 | 9/14/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/14/2000 at 09:27:42. Contact: ###-####. exercise room ceiling ele r/i, southwest area, 1st floor. 9/14/2000 7:54:50 PM
|
Electrical Rough-In | 9/7/2000 | 9/8/2000 | 9/8/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/07/2000 at 15:21:08. Contact: ###-####. 2nd floor corridor ceiling r/i. 9/10/2000 6:09:32 PM
|
Electrical Rough-In | 9/5/2000 | 9/6/2000 | 9/6/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 15:17:55. Contact: ###-####. women's locker room and office; ceiling ele r/i. 9/6/2000 12:51:52 PM
|
Electrical Rough-In | 8/31/2000 | 9/1/2000 | 9/1/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/31/2000 at 12:58:23. Contact: ###-####. ele r/i, c. v. room (soffit lighting); pool area, temporary occupancy. 9/1/2000 8:20:27 PM
|
Electrical Rough-In | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 08/15/2000 at 09:42:14. Contact: ###-####.
|
Electrical Rough-In | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 10:47:54. Contact: ###-####.
temp. occup. in natatorium area, bathrm., offices, storage area. 8/11/2000 11:19:56 AM
|
Electrical Rough-In | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 10:47:54. Contact: ###-####. kt sub-feed raceway,for cover. 8/14/2000 7:48:14 AM
|
Electrical Rough-In | 8/7/2000 | 8/8/2000 | 8/8/2000 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 08/07/2000 at 11:59:36. Contact: ###-####. Ok bonding office pad pool 8/10/00 11:29:40 AM
|
Electrical Rough-In | 8/2/2000 | 8/3/2000 | 8/3/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/02/2000 at 10:02:44. Contact: ###-####. conference, clearances. 8/3/2000 12:25:22 PM
|
Electrical Rough-In | 7/28/2000 | 7/31/2000 | 7/31/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 07/28/2000 at 14:43:10. Contact: ###-####. childrens pool-bonding, room#123 ele r/i, 1-wall. 7/31/2000 6:22:40 PM
|
Electrical Rough-In | 7/24/2000 | 7/25/2000 | 7/25/2000 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/24/2000 at 09:11:58. Contact: ###-####. Ok part pool bonding. 7/26/00 10:51:46 AM
|
Electrical Rough-In | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 09:33:03. Contact: ###-####. Ok cover rms. B50, B46, 47, 48 7/14/00 2:37:36 PM
|
Electrical Rough-In | 7/12/2000 | 7/12/2000 | 7/12/2000 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 07:10:37. Contact: ###-####. Rm. 104 ok cover 7/13/00 1:34:36 PM
|
Electrical Rough-In | 7/6/2000 | 7/7/2000 | 7/7/2000 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 14:01:24. Contact: ###-####. Ok final Rm IDO 7/10/00 10:25:43 AM
|
Electrical Rough-In | 7/6/2000 | 7/7/2000 | 7/6/2000 | A | CANC |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 13:29:01. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 07/06/2000 at 14:00:05.
|
Electrical Rough-In | 6/29/2000 | 6/30/2000 | 6/30/2000 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 06/29/2000 at 16:03:02. Contact: ###-####. ceiling rm 110 ok cover 7/3/00 8:19:55 AM
|
Electrical Rough-In | 6/26/2000 | 6/26/2000 | 6/26/2000 | P | PASS |
Jim Schmer
|
|
|
Scheduled by a contractor via Hello! on 06/26/2000 at 07:19:17. Contact: ###-####. partial R/I for Rm 110 ceiling 6/28/00 1:39:10 PM
|
Electrical Rough-In | 6/22/2000 | 6/23/2000 | 6/23/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 06/22/2000 at 12:47:53. Contact: ###-####. Basement hallway R/I; ceiling 6/23/00 3:11:44 PM
|
Electrical Rough-In | 6/14/2000 | 6/15/2000 | 6/15/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 06/14/2000 at 12:58:45. Contact: . Pool bonding- cup holders, & railings 6/15/00 1:42:12 PM
|
Electrical Rough-In | 6/13/2000 | 6/14/2000 | 6/14/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 06/13/2000 at 11:49:43. Contact: . Basement: RM. B-20 ceiling R/I 6/14/00 12:15:47 PM
|
Final | 6/13/2000 | 6/14/2000 | 6/13/2000 | A | CANC |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 06/13/2000 at 11:36:49. Contact: . Disp set to [CANC] by a contractor via Hello! on 06/13/2000 at 11:48:20.
|
Electrical Rough-In | 6/7/2000 | 6/8/2000 | 6/8/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 06/07/2000 at 15:14:02. Contact: ###-####.
Ceiling R/I, rooms 137 & 125
|
Electrical Rough-In | 5/16/2000 | 5/16/2000 | 5/16/2000 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 05/16/2000 at 07:39:09. Contact: ###-####. Ok cover pool bonding. 5/17/00 1:49:28 PM
|
Electrical Rough-In | 5/11/2000 | 5/12/2000 | 5/12/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 05/11/2000 at 13:15:37. Contact: ###-####. 2 office ceilings; ele. R/I. 5/15/00 10:52:08 AM
|
Electrical Rough-In | 5/10/2000 | 5/11/2000 | 5/11/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 05/10/2000 at 12:55:25. Contact: ###-####. Natatorium bathroom ele. R/I. 5/11/00 2:41:18 PM
|
Electrical Rough-In | 5/8/2000 | 5/9/2000 | 5/9/2000 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 05/08/2000 at 10:36:40. Contact: ###-####. Ok cover front entry 5/9/00 12:17:49 PM
|
Electrical Rough-In | 5/2/2000 | 5/2/2000 | 5/2/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 05/02/2000 at 08:51:33. Contact: ###-####. 2nd floor room #216 ele. R/I walls. 5/3/00 3:32:04 PM
|
Electrical Rough-In | 4/25/2000 | 4/26/2000 | 4/26/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 04/25/2000 at 13:06:30. Contact: ###-####. Hallway #152; ceiling R/I 4/26/00 11:54:53 AM
|
Electrical Rough-In | 4/21/2000 | 4/21/2000 | 4/21/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 04/21/2000 at 07:13:12. Contact: ###-####. Ceiling R/I; hallway #217 4/24/00 9:00:54 AM
|
Electrical Rough-In | 4/19/2000 | 4/19/2000 | 4/19/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 04/19/2000 at 08:10:58. Contact: ###-####. Hallway #134, 1st floor- ceiling R/I 2-bathrooms (basement). Temp/occ. 4/21/00 8:54:20 AM
|
Electrical Rough-In | 4/17/2000 | 4/18/2000 | 4/18/2000 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 04/17/2000 at 12:00:25. Contact: ###-####. Ceiling ok cover front office part 4/18/00 11:47:11 AM
|
Electrical Rough-In | 4/10/2000 | 4/11/2000 | 4/11/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 04/10/2000 at 15:17:37. Contact: ###-####. Northend gymnasium ceiling Ele. R/I 4/12/00 8:37:50 AM
|
Electrical Rough-In | 4/7/2000 | 4/10/2000 | 4/10/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 04/07/2000 at 13:59:33. Contact: ###-####. St. Al's room, 1st floor ceiling R/I 4/11/00 11:23:43 AM
|
Electrical Rough-In | 3/31/2000 | 3/31/2000 | 3/31/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/31/2000 at 07:47:32. Contact: ###-####. Room #161; Room #106 temp. occupancy 4/3/00 8:41:02 AM
|
Electrical Rough-In | 3/20/2000 | 3/21/2000 | 3/21/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/20/2000 at 11:55:23. Contact: ###-####. 2 bathrooms/basement Ele. R/I 3/21/00 11:42:22 AM
|
Electrical Rough-In | 3/16/2000 | 3/16/2000 | 3/16/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/16/2000 at 08:02:24. Contact: ###-####. Youth activity; center ceiling R/I. 3/17/00 10:37:24 AM
|
Electrical Rough-In | 3/14/2000 | 3/14/2000 | 3/14/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/14/2000 at 10:10:23. Contact: . 1st floor counter/island Ele. R/I. 3/16/00 11:12:25 AM
|
Electrical Rough-In | 3/3/2000 | 3/3/2000 | 3/3/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 10:00:03. Contact: ###-####. Physical prep room. 3/6/00 11:16:51 AM
|
Electrical Rough-In | 2/28/2000 | 2/29/2000 | 2/29/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/28/2000 at 13:38:14. Contact: ###-####. Pool bending. 2/29/00 3:13:57 PM
|
Electrical Rough-In | 2/25/2000 | 2/28/2000 | 2/28/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/25/2000 at 07:40:08. Contact: ###-####. Baths- roof top. 2/28/00 2:35:08 PM
|
Electrical Rough-In | 2/11/2000 | 2/14/2000 | 2/14/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 13:26:00. Contact: . Walls; main entry. 2/15/00 9:30:38 AM
|
Electrical Rough-In | 2/4/2000 | 2/7/2000 | 2/7/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/04/2000 at 11:36:36. Contact: ###-####. North office area; Ele. R/I. 2/7/00 1:36:58 PM
|
Final | 2/7/2000 | 2/7/2000 | 2/7/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/07/2000 at 11:24:32. Contact: . Temporary occupancy : 1st floor north addition
|
Electrical Rough-In | 1/27/2000 | 1/27/2000 | 1/27/2000 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 07:37:43. Contact: ###-####. ceiling r/i north addition 1st floor 1/28/00 9:46:41 AM
|
Electrical Rough-In | 1/5/2000 | 1/6/2000 | 1/6/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/05/2000 at 15:11:49. Contact: ###-####. Yack-area, wall R/I; Men's dry-off area, walls R/I.
|
Electrical Rough-In | 12/21/1999 | 12/22/1999 | 12/22/1999 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 12/21/1999 at 13:38:21. Contact: ###-####. Special needs 1st floor ceiling R/I- 3 rooms.
|
Electrical Rough-In | 12/7/1999 | 12/8/1999 | 12/8/1999 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 12/07/1999 at 08:45:28. Contact: ###-####. Northend offices.
|
Final | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 13:08:06. Contact: ###-####. Final ok laundry room.
|
Electrical Rough-In | 11/1/1999 | 11/1/1999 | 11/1/1999 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 07:51:22. Contact: ###-####. Ceiling: ELE R/I; front office area; mens locker room.
|
Electrical Rough-In | 10/4/1999 | 10/4/1999 | 10/4/1999 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 10:34:24. Contact: ###-####.\ ok to cover so ea concrete wall pool area
|
INSP - Electrical Rough-In | 8/11/1999 | 8/12/1999 | 8/12/1999 | A | PART |
Jack Frank
|
|
|
08/12/99 315 - Scheduled by Hello!. Contact phone is [8882523]. u/g ok
|
INSP - Electrical Rough-In | 7/14/1999 | 7/14/1999 | 7/14/1999 | P | PART |
Marv Burrus
|
|
|
07/14/99 403 - Scheduled by Hello!. Contact phone is [8905971]. MAIN SERVICE SWITCHGEAR.
|
INSP - Electrical Rough-In | 7/6/1999 | 7/6/1999 | 7/6/1999 | P | PASS |
Jim Schmer
|
|
|
Scheduled by Hello!. Contact phone is [8905971].
|
INSP - Electrical Rough-In | 5/18/1999 | 5/19/1999 | 5/19/1999 | A | PART |
Marv Burrus
|
|
|
05/18/99 403 - ###-#### COLLEEN//CONFERENCE DISCUSSED CLEARENCES ABOVE MAIN SWITCH GEAR; LEFT CORRECTION NOTICE, (NE
|
INSP - Electrical Rough-In | 5/14/1999 | 5/14/1999 | 5/14/1999 | | PART |
Marv Burrus
|
|
|
05/14/99 403 - ###-####//UNDERGROUND PVC CONDUIT FEEDERS. OK
|