DOC - Permit Finaled | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 7/12/2004 | 7/15/2004 | 7/15/2004 | A | DONE |
Steven Webb
|
|
|
Requested by contractor Most property hydroseeded, unsure if seed will survive considering the time of year is was sprayed. Vertical bank cut bare soil. 7/19/2004 1:46:19 PM
|
Site Final | 4/7/2004 | 4/12/2004 | 4/12/2004 | A | FAIL |
Steven Webb
|
|
|
Slopes around the house need stablization. Informed rp. 4/12/2004 9:10:49 AM
|
Site Preparation | 4/28/2003 | 4/30/2003 | 4/30/2003 | A | PASS |
Steven Webb
|
|
|
Removed correction notice--continue to maintain. 4/30/2003 9:31:09 AM
|
Site Preparation | 4/25/2003 | 4/28/2003 | 4/28/2003 | A | PART |
Steven Webb
|
|
|
Damon--###-#### Removed stop work order but c/notice remains--informed rp to complete items on c/n or stop work will be re-issued. 4/28/2003 10:35:27 AM
|
Site Preparation | 4/24/2003 | 4/25/2003 | 4/25/2003 | A | DONE |
Steven Webb
|
|
|
More conference than inspection--Reviewed approved plan with RP--Stop work will stand until provisions of plan are completed. Will follow up on Monday am. 4/25/2003 1:23:45 PM
|
Site Preparation | 4/24/2003 | 4/24/2003 | 4/24/2003 | A | FAIL |
Steven Webb
|
|
|
J. Rogers issued stop work, Damon--RP--###-####. 4/24/2003 9:45:33 AM
|
Site Preparation | 4/23/2003 | 4/23/2003 | 4/23/2003 | A | FAIL |
Steven Webb
|
|
|
C/N posted--Completed by 5: 00 pm today. Damon--###-#### 4/23/2003 10:03:38 AM
|