Site Final | 8/18/2008 | 8/18/2008 | 8/18/2008 | P | PASS |
Clint A Smith
|
|
|
Site is stabilized.
|
Tracking Control | 10/13/2006 | 10/13/2006 | 10/19/2006 | P | DONE |
Steven Webb
|
|
|
Re-inspection
|
Complaint Inspection | 10/13/2006 | 10/13/2006 | 10/13/2006 | A | FAIL |
Steven Webb
|
|
|
Complaint received regarding tracking of dirt onto hard surface from project at Grand Forest. No rock construction entrance. This occured on 10/12/06. Informed rp to correct and that after many violations from this contractor no more corrrections but will proceed directly to Stop Work Orders in the future.
|
Random Inspection | 10/9/2006 | 10/9/2006 | 10/9/2006 | P | PART |
Aimee Hughes
|
|
|
Contacted RP about status of project. Bare soil along Hwy 21 will be hydroseeded at the end of the week after the sewer line extension is completed.
|