Aging Inspection | 3/9/2010 | 3/9/2010 | 3/9/2010 | | DONE |
Jim Storey
|
|
|
|
Site Final | 3/9/2010 | 3/9/2010 | 3/9/2010 | A | PASS |
Jim Storey
|
|
|
|
Site Final | 7/15/2009 | 7/15/2009 | 7/16/2009 | P | CANC |
Eric Strole
|
|
|
|
BMP Violation | 10/24/2006 | 10/24/2006 | 10/24/2006 | A | PART |
Steven Webb
|
|
|
Verbal to RP: Sediment barrier needed at various locations, mainly on the east side next to the open ditch. Sweeping of hard surface needed. Maintance of existing sediment barrier.
|
BMP Violation | 9/18/2006 | 9/19/2006 | 9/19/2006 | A | PASS |
Steven Webb
|
|
|
Re-inspection: Sediment barrier back in place at drainage.
|
BMP Violation | 9/18/2006 | 9/18/2006 | 9/18/2006 | A | FAIL |
Steven Webb
|
|
|
Observed dirt over silt fence at drainage ditch, informed contractor. Contractor to correct problem and install structual sediment barrier by days end. Will follow up.
|
BMP Violation | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | PART |
Steven Webb
|
|
|
Correction to rp: Complete construction entrance and site is in need of dust abatement. Contractor said work will be done today on entrance and site will have a water truck working in the p.m. Ody--###-####.
|