Site Final | 9/4/2009 | 9/4/2009 | 9/4/2009 | P | PASS |
Mike Jordan
|
|
|
Final stabalization has been completed.
|
Random Inspection | 10/2/2008 | 10/2/2008 | 10/2/2008 | P | FAIL |
Clint A Smith
|
|
|
Left a message with the RP and also Kenny Kiel (###-####)
Need to sweep up all hard surface of sediment and debris off of all hard surfaces. Will re-inspect on 10/3/08.
|
BMP Violation | 3/4/2008 | 3/5/2008 | 3/5/2008 | A | PART |
Clint A Smith
|
|
|
Site is looking better. 98% of all tash has been picked up and contained. Silt fence has been installed around the perimeter of project. All but one outfall has been protected. Will re-inspect on Friday to see what has been done to protect the outfall at the West end of project. CAS #460 ###-####
|
Conference | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PART |
Steven Webb
|
|
|
Met with rp, contractor, esc inspector 460. Outlined the necessary requirements to avoid a stop work order. Complete items by end of day of March 4, 2008.
|
BMP Violation | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PART |
Clint A Smith
|
|
|
Working actively on Correction Notice. Will re-inspect on Wensday in the am. CAS #460
|