Site Final | 7/21/2008 | 7/28/2008 | 7/28/2008 | A | PASS |
Clint A Smith
|
|
|
Duplicate.
|
Site Final | 7/23/2008 | 7/23/2008 | 7/23/2008 | A | PASS |
Clint A Smith
|
|
|
All disturbed soil has been stabilized with a tackifier w/ a seed mulch. CAS
|
Random Inspection | 7/18/2008 | 7/18/2008 | 7/18/2008 | P | PASS |
Jim Storey
|
|
|
|
General Inspection | 7/10/2008 | 7/10/2008 | 7/10/2008 | P | PASS |
Mike Kinnear
|
|
|
sign posted site looks fine
|
General Inspection | 7/8/2008 | 7/8/2008 | 7/8/2008 | P | PART |
Mike Kinnear
|
|
|
sign posted, asphalt installed, & land scaping is started
|
BMP Violation | 6/18/2008 | 6/20/2008 | 6/23/2008 | A | PASS |
Clint A Smith
|
|
|
trash has been cleaned up. CAS #460
|
Random Inspection | 6/18/2008 | 6/18/2008 | 6/18/2008 | A | FAIL |
Clint A Smith
|
|
|
The slope next to parkcenter is greater than 2%. Waiting on an answer from the project super when landscaping will be completed on the front section. Also trash piles around the project need to be picked up and placed into the trash container. Will re-inspect on 6/20/08. CAS #460
|
General Inspection | 6/5/2008 | 6/5/2008 | 6/5/2008 | P | PART |
Steven Webb
|
|
|
Verbal to RP; Need to pick up trash, repost sign on job trailer, monitor trackout, improper concrete washout.
|
Random Inspection | 6/4/2008 | 6/4/2008 | 6/4/2008 | P | PASS |
Mike Kinnear
|
|
|
ok sign posted & site being prep. for asphault
|
General Inspection | 6/3/2008 | 6/3/2008 | 6/3/2008 | A | PASS |
Mike Kinnear
|
|
|
sign posted site being prep. for asphault
|
BMP Violation | 4/2/2008 | 4/2/2008 | 4/2/2008 | P | PASS |
Clint A Smith
|
|
|
ESC Sign posted at front of project at the Construction Entrance. CAS #460
|
Site Preparation | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Clint A Smith
|
|
|
Entrance has been constructed per the EC plan. Perimeter fencing will be installed shortly. Told RP to keep an eye on the area to the right of the entrance for potentail run off. CAS#460 ###-####
|